Referendum
Statement: This project consists of acquisition of approximately 40
acres of land necessary to construct the future Airport Commercial Terminal
Facility with an entrance from US Highway 78.
Project
Location: Lexington Road (Hwy 78)
- Original
Project Budget:
- (Fixed)
$1,067,822
- (Variable)
$0
- Additional
SPLOST Revenues Allocated: None
- Additional
Funding: General
Fund :
$0
- Total
Project Budget: $1,067,822
- Annual
Operating Budget Impact: $0
- Budgets
-
FY02: $0
- FY03:
$0
-
FY04: $0
-
FY05: $0
-
FY06: $0
(Variable)
PROJECT
CONCEPT / DESCRIPTION:
- The
Mission of this project is to acquire land adjacent to the
Athens Airport and ACC Correctional Institute for construction of
a future Commercial Terminal Facility.
- This
project will fund the acquisition of 39.23 acres of land in the purchase
amount of $935,000. $10,000 of Earnest Monies has been paid to the property
owner up front. At the time of Closing, set for August, 2000, the balance
will be provided to the existing property owner.
- To
the extent that not all of the projects funds are expended on land acquisition,
the remaining balance of funds is envisioned to be utilized for site
preparation including surveying, wetland delineation and other environmental
analysis, and preliminary design services for the Future Commercial
Terminal Facility.
Project
Design Consultant:
None Required
Sponsoring
Department: Airport
Department
Director: Tim Beggarly
Associated
Organizations:
Airport Authority
Other
Interested Organizations: None
Verifications/Approvals:
Date - References:
- Mayor
& Commission: July 05, 2000 - SP2K Project Submittal Form
- SP2K
Citizens Advisory Comm: June 07, 2000
- Managers
Office: June 01, 2000
- Responsible
Department: May 25, 2000
Current
Status:
Completed.
Action
Since Last Report: PROJECT IS COMPLETE.
Comments:
|