| REFERENDUM
STATEMENT: -
This project consists of constructing a new Transit Bus
Transfer Center for ACC Buses, UGA Buses, and Inter-City Buses, Parking
for approximately 100 vehicles (shared facility with the Classic Center),
Commuter Rail Platform (utilized to link Athens to Atlanta by rail),
Kiss and Ride drop-off area, Pedestrian Bridge Connector, and on-site
infrastructure such as access roads, and utility upgrades. It will also
include necessary off-site improvements to East Broad Street and Foundry
Street. This project is a continuation of the existing
SPLOST IV Program.
- Budget:
$7,000,000 Fixed
- Annual
Operating Expense: $ 98,000
Current
Status: Phase
IV - Construction
Actions
Since Last Report:
Construction: Project
is 92% complete
- Package “A” (Roadway & Civil)
- Package A.1 (Building Pad / Detention Pond / New Hickory Street)
- Substantially Complete.
- Package A.2 (East Broad Street Improvements) - Sub-Project
is 90% Complete.
- Pedestrian light bases are proceeding along with the sidewalk
installation on new Hickory and E. Broad Streets.
- Final curb and gutter work/repairs are being made.
- Handicap ramps and sidewalks are in progress.
- Sub-Project is projected to be complete in May 2006.
- Package “B” (Building) - Sub-Project is 50% Complete
- Curb and Gutter along with concrete bus bays are complete.
- Sub base for asphalt drives is underway.
- Site electrical is complete.
- Cast stone and brick veneer are progressing and is about 95% complete.
- Plumbing and HVAC rough is complete.
- Interior gypsum drywall is approximately 90% complete.
- Elevator equipment installation is complete.
- Sub-Project schedule is now projected to be substantially complete
by the end of April 2006.
Images:
Related
Documents:
|