| Referendum
Statement: This
project consists of the design and construction and/or improvements of such
items as: sidewalk, access ramps, pedestrian signals and crossings, school
zone crossings, and general pedestrian improvements. Specific projects will
be developed on a yearly basis and prioritized utilizing a ranking system.
Project
Location: Various sidewalk projects throughout the entire Athens-Clarke
County area.
- Original
Project Budget:
- (Fixed)
$ 800,000
- (Variable)
$ 106,670
- Additional
SPLOST Revenues Allocated: None
- Additional
Requested Funding from General Fund FY01-FY05: $615,000
(FY02-FY05 Projected)
- Total
Project Budget: $ 1,521,670
- Operating
Budget Impact: $0
- Budgets
- FY01:
$140,000
- FY02:
$165,000
-
FY03: $165,000
-
FY04: $165,000
-
FY05: $165,000
-
FY06: $106,670 (Variable)
PROJECT CONCEPT:
- This project
is considered an REOCURRING Project, which is envisioned to be
appropriated funds on an Annual basis.
- This project
is envisioned to expand and/or improve the existing sidewalk system
throughout Athens-Clarke County through the combined utilization of
SPLOST 2000 funds, and other available funding sources.
- Sidewalk
improvement sub-projects are identified, prioritized and budgeted in
accordance with the Mayor and Commission adopted Sidewalk Improvement
Program.
- The Projects
Objective is to increase the number of linear feet of sidewalks
constructed and/or improved throughout Athens-Clarke County.
- Right-of-way
and easement acquisitions will be evaluated and accomplished on a specific
sub-project basis.
Project
Design Consultant: Arcadis Geraghty & Miller
Sponsoring
Department: Transportation & Public Works
Department
Director: David Clark
Associated
Organizations: None
Other
Interested Organizations: None
Verifications/Approvals:
Date - References:
- Mayor
& Commission: November 2, 1999, March 2, 2000
- SPLOST
Advisory Comm: August 30, 2000
- Managers
Office: October 27, 1999
- Responsible
Department: August 22, 2000
Current
Status:
- Group
A - (Phase I and II) - Project is complete.
- Group
B - (Barnett Shoals Road, Old Lexington Road, Tallassee Road) - Project
is complete.
- Group
C - (Tallassee Road & Mitchell Bridge Road) - Project
is complete.
- Group
D
- (Whit Davis Road, Old West Broad, Roberts Road) - Project
is complete.
|