|
Referendum
Statement: This project consists of the installation of a control
system for the Mechanical systems, allowing the ability to better manage
energy. It will also include
replacement of existing dividing walls in the ballroom with higher rated
acoustical walls and the purchase of lighting instruments for the theater.
Project
Location: Classic Center.
- Original
Project Budget:
- (Fixed)
$ 691,900
- (Variable)
$ 00
-
Additional SPLOST Revenues Allocated: None
-
Additional Requested Funding from: None
- Total
Project Budget: $ 691,900
- Operating
Budget Impact: $0
- Budgets
-
FY01: $691,900
-
FY02: $00
-
FY03: $00
-
FY04: $00
-
FY05: $00
-
FY06: $00 (Variable)
PROJECT DESCRIPTION:
This
project consists of four Elements and they are as follows (Three
Elements are included in this Project Description. The fourth will be
brought forward in the near future as part of a revised Project Description):
- Element
1 Energy Management System Improvements; This element is
further broken down into two sub-components of work necessary to upgrade
the Classic Centers current systems. They are as follows:
- 1A
Energy Control System; This first sub-component includes
the installation of a control system including computer software
that will enable the Classic Centers Plant Manager the ability
to control all Mechanical Operating Systems from two central points.
In addition, this system will alert the Plant Manager of any problems
within the system. It is estimated that this type of improvement
will provide savings in the range of $30,000 per year, greatly improving
customer satisfaction by better control of the building environment.
Total estimated cost for this sub-component is $40,000.
- 1B
Energy Management System; The second sub-component
includes the installation of capacitors on all electrical operating
systems in the Classic Center. The capacitors work with the Energy
Control System to narrow the normal energy curve resulting in significantly
lower energy costs. It is estimated that these improvements will
reduce the overall energy cost for the Classic Center by 25%. Total
estimated cost for this sub-component is $78,000.
- 1C
HVAC Improvements; This third sub-component is to correct
the numerous customer complaints regarding the lack of proper temperature
control in the theater, and employee complaints about the temperature
in the box offices. In an effort to correct this situation, detailed
drawings and specifications have been developed with the assistance
of the original HVAC engineer and Paul Martin. The HVAC Improvements
include several steps; First, is the installation of additional
heating units on the main stage. Second, is the installation of
floor mounted electric heaters in the main orchestra level. Third,
is the installation of extensions to the highest duct over the mezzanine
level of the theater. The original design was meant to pull the
air from the supply duct to the return, but has proven ineffective.
The mezzanine level duct is also located in a position
that makes it ineffective, and the supply air is bypassing the customers
seated in the mezzanine level. The installation of duct extensions
will provide significantly increased
air flow to the proper areas and correct the problem. (See Exhibit
B for drawings illustrating these improvements).
- In
addition, two other areas that cause The Classic Center to waste
energy and increase cost are two small areas (the box office and
the theater boardroom) that are currently cooled/heated by the theaters
central mechanical unit. Currently, when cooling/heating the box
office, it is linked with cooling/heating the entire fire hall,
and the cooling/heating of the theater boardroom is linked with
cooling/heating the entire theater. This problem is envisioned to
be corrected by installing a small mechanical unit in the box office,
and by installing additional duct work and separate thermostatic
controls in the theater boardroom. Total estimated cost for this
sub-component is $135,000.
- Total
estimated costs for Element 1 sub-components is $253,000.
- Element
2 Theatrical Lighting Improvements; This element is further
broken down into two sub-components of work necessary to upgrade the
Classic Centers current systems. They are as follows:
- 2A
Exhibit Hall Structural Support Modifications; The scope
of work associated with this sub-component is envisioned to consist
of modifications to the structural steel roof joists. An qualified
structural engineer was employed to develop necessary modifications
necessary to strengthen the supports and allow additional weight
sufficient to meet the needs of the lighting systems of the Classic
Center customers. This sub-component has been purchased and is eligible
for reimbursement to the Classic Center Authority. Total cost for
this sub-component is $4,974.
- 2B
Lighting Truss System; A portable lighting truss
system will provide industry standard lighting towers with manual
crank devices, instruments, dress kit, and portable dimmer system.
This system will allow the Classic Center the flexibility of controlling
the intensity of lighting used during performances and lectures.
The system is designed to allow for a safe solution to our existing
customer requests for theatrical lighting in the ballrooms and exhibit
halls. This sub-component has been purchased and is eligible for
reimbursement to the Classic Center Authority. Total cost for this
sub-component is $22,426.
- 2C
Theatrical Lighting Instruments; A full accompaniment
of over 200 theatrical stage lighting instruments is envisioned
to be purchased and used to stage a multitude of events throughout
The Classic Center. These instruments can be used for concerts,
Broadway shows, and corporate / social events that need to be provided
with this level of lighting. Currently, our customers have to rent
such lighting from other companies. Total estimated cost for this
sub-component is $66,739.
- Total
estimated costs for Element 2 sub-components is $94,139.
- Element
3 Wall Partitions; This element is envisioned to provide
replacement of three primary wall partitions located between the four
largest ballrooms. The new wall partitions will have a 50% increase
in sound protection rating and will have a new top seal installed. This
will greatly reduce the unwanted sound transfer between rooms. By reducing
the sound transfer we will improve customer satisfaction and maximize
our booking schedule. Operationally, the wall pockets into which the
walls fold for storage will also receive slight modification. These
storage areas will have installed a 45-degree angle iron to make it
easier in moving the panels in and out of the wall pockets. This will
save time in setting up and tearing down the walls for events, plus
reduce the maintenance of the wall units. Finally, all of the walls
will be covered in carpeting so as to improve the reverberation within
the rooms.
- Total
estimated cost for this Element is $190,000.
Project
Design Consultant: N/A
Sponsoring Department: The
Classic Center
Department Director: Paul
Cramer
Associated Organizations: The
Classic Center Authority
Other Interested Organizations:
Verifications/Approvals:
Date - References:
- Mayor
& Commission: Aug. 01, 2000 - SPLOST Project Request
- SPLOST
Advisory Comm: July 12, 2000
- Managers
Office: July 12, 2000
- Responsible
Department: July 11, 2000
Current
Status: Construction
Phase (Installation).
Action
taken since last Report:
- Element
1 - Energy Management System Improvements:
- 1A
- Energy Control System; Energy Control Systems, Inc. is complete
- 1B
- Energy Management System; To be deleted. Element 1A can provide
all required services.
- 1C
- HVAC Improvements; Work is progressing and is currently 95% complete.
- Element
2 - Theatrical Lighting Improvements:
- 2A
- Exhibit Hall Structural Support Modifications; Project
is Complete
- 2B
- Lighting Truss System; Project
is Complete
- 2C
- Theatrical Lighting Instruments; Project
is Complete
- Element
3 - Wall Partitions:
- Acousti,
Inc. - Project is complete
- Element
4 - Campus / Life Cycle Plan:
|