PROJECT
11 - PARKS FACILITIES
Campaign
Statement: Repair and upgrade current Leisure Services Dept. and Arts
and Environmental facilities to ensure that major infrastructure problems
and repairs related to public safety and accessibility are addressed.
Project
Location: Parks Facilities throughout Athens-Clarke County.
Original
Project Budget: $ 2,378,200
Additional
Funding: $130,000 (Amendment 2 - April 4,
2000)
Revised
Project Budget: $2,430,200
Operating
Budget Impact: $1,690.00/Year
PROJECT
DESCRIPTION: The projects have been prioritized by the Athens-Clarke
County Leisure Department along with input from the Manager’s Office and
SPLOST Advisory Committee. SPLOST funds will be expended to complete as
many of the Renovations, Additions and New Structures as possible.
Group
O Project Descriptions: These projects are those that were either
started or completed prior to the development of the current Project Description
approval process.
- SUB-PROJECT
SCNC3.1 - Sandy Creek Nature Center - Security System: This sub-project
consists of replacing the existing security systems for all buildings
within this park. This installation will be accomplished under one
contract and receive quotes utilizing normal A-CC Purchasing requirements.
Status: Project is Complete
- SUB-PROJECT
BP2.1 - Bishop Park - Replacement of Gymnasium Flooring: This sub-project
consists of replacing the existing flooring systems for the playing
surfaces within the Gymnasium building. This installation will be accomplished
under one contract and receive quotes utilizing normal A-CC Purchasing
requirements. Status: Project
is Complete
- SUB-PROJECT
BP3.1 - Bishop Park - Renovation of Swimming Pool: This sub-project
consists of renovating the existing swimming pool within this park.
It consists of refurbishing the existing pool walls with a new Fiberglass
system, replacement of the gutters and skimmers, enlargement of the
pool itself to allow competition swim meets, and covering the pool deck
with a synthetic cool deck. This construction will be accomplished under
one contract and receive quotes utilizing normal A-CC Purchasing requirements.
Status: Project
is Complete
- SUB-PROJECT
MP4.1 - Memorial Park - Surface Pedestrian Path: This sub-project
consists of constructing a concrete walk around the existing lake within
this park. This construction will be accomplished utilizing A-CC Leisure
Services Department staff. Status: Project
is Complete.
- SUB-PROJECT
MP5.1 - Memorial Park - Resurface Playground Fall Area: This sub-project
consists of replacing the existing Playground surface with shredded
tires. This purchase and installation will be accomplished utilizing
A-CC Leisure Services Department Staff. Status: Project
is Complete
- SUB-PROJECT
SM1.1 - Showmobile: This sub-project consists of replacing the existing
Showmobile with a new state of the art hydraulic-self leveling one.
This purchase of this piece of equipment will be accomplished under
one contract and receive bids utilizing normal A-CC Purchasing requirements.
Status: Project
is Complete
- SUB-PROJECT
ROSP1.1 - Rocksprings Community Center - Security System: This sub-project
consists of replacing the existing security systems for all buildings
within this park. This installation will be accomplished under one contract
and receive quotes utilizing normal A-CC Purchasing requirements. Status: Project
is Complete
GROUP
A - SUB-PROJECT DESCRIPTIONS:
- SUB-PROJECT
BP1.1 - Bishop Park Pool House Renovations / ADA Improvements:
The existing Pool House, (approximately 2,168 SF ), will be totally
renovated. New Plumbing / Fixtures, Mechanical, Electrical / Fixtures
will be installed. The interior will be constructed to meet ADA requirements
in the shower facilities and toilet stalls. A new 427 SF Gazebo / Lifeguard
House will be constructed. This project will be bid utilizing normal
ACC Purchasing Requirements. Status:
Project is Complete.
- SUB-PROJECT
SCP3.1 - Sandy Creek Park Large Picnic Shelter: This sub-project
consists of construction of a new pre-manufactured picnic shelter, (3,312
SF ), that can accommodate 300 people. It will also consist of a smaller
pre-manufactured shelter, (676 SF), that will contain the ADA accessible
men’s and women’s restrooms and outdoor sinks. The site will be landscaped
and parking for three vehicles will be constructed. This project will
be bid utilizing normal ACC Purchasing Requirements. The Picnic tables
and chairs will be purchased under separate contract. Status:
Project is Complete.
- SUB-PROJECT
SCNC1.1 & SCNC1.2 - Sandy Creek Nature Center Renovations and ADA
Improvements: This sub-project consists of the renovation of
the existing restrooms and hallway adjacent to the fireside office.
It will also include the addition of an attic space above the existing
restroom and hallway. The building’s electrical systems will be updated
to meet building code requirements. The exterior deck will be expanded
by 455 SF to provide an observation area over the duck pond. An ADA
accessible ramp will be extended from this deck so that disabled persons
will be able to access the other side of the building. In addition,
an outdoor teaching area with seating will be constructed. This project
will be bid utilizing normal ACC Purchasing Requirements. Status:
Project is Complete.
- SUB-PROJECT
MP1.1 - Memorial Park New Restroom Facility: This sub-project
consists of a new ADA accessible restroom facility for Memorial Park.
The facility will be 455 SF and contain a men and women’s restroom.
The project will also consist of an ADA accessible trail to be constructed
between the existing trail around the lake and the new facility. This
sub-project will be constructed with Leisure Services Department Staff.
Status:
Project is Complete.
- SUB-PROJECT
EACP1.1 - East Athens Community Park - Tennis Court Replacement:
This sub-project consists of the demolition of the existing tennis court
at East Athens Community Park and the construction of two new courts.
It will also consist of the required new perimeter fencing and nets.
This project has been bid utilizing normal ACC Purchasing Requirements.
Status:
Project is Complete.
GROUP
B - SUB-PROJECT DESCRIPTIONS:
- SUB-PROJECT
MP2.1 - Memorial Park Pool House Renovations / ADA Improvements:
The existing Pool House will be renovated to add an ADA accessible restroom.
Leisure Services department’s staff will accomplish construction. Status:
Project is complete.
- SUB-PROJECT
SCP2.1: & SCP4.1 - Sandy Creek Park Patrol Dock and ADA access to
Beach: This sub-project consist of construction of a new Beach Rental
building (395 SF). Included within this building will be an ADA accessible
restroom, (to serve the beach area), a concession center, and boat rental
/ storage. The building will require a new septic field be constructed.
The access drive will be regraded to provide ADA access from the main
parking lot to the beach area. The Beach Rental building will have a
concrete deck around it and two ADA parking spaces. An ADA accessible
boardwalk / deck will be constructed to provide accessibility from the
asphalt drive to the beach, lake, and canoe rental area. A Premanufactured
dock, which includes an H shape dock, covered boat storage, and a connector
to the Beach rental building will be purchased and constructed under
a separate contract. This project will be bid utilizing normal A-CC
Purchasing requirements. Status: Project
is Complete.
- SUB-PROJECT
SCP5.1 - Sandy Creek Park Beach Wiring Problem: This sub-project
consists of replacing the existing wiring for all electrical service
to the beach area. This project will be accomplished by Jackson Electric
Membership. Status:
Project is complete.
- SUB-PROJECT
SCP6.1 - Sandy Creek Park - Replace Fishing Pier Decking: This sub-project
consists of replacing the wooden decking and all necessary sub-structure
of the Sandy Creek Park Fishing Pier. The construction of this project
is being accomplished by Leisure Services department staff. Status:
Project is complete.
- SUB-PROJECT
SCNC4.1 & 5.1 - Sandy Creek Nature Center - Interpretative Trail
and General Site Equipment: This sub-project consists of approximately
500 linear feet of exterior boardwalk trail system. This trail will
be ADA accessible and have its origin begin at the Natural Science &
Appropriate Tech. Center. The trail will have as many as 5 teaching
nodes (platforms) connected to the boardwalk. Staff will utilize these
teaching nodes as outdoor classrooms. This project will be bid utilizing
normal A-CC Purchasing requirements. Status:
Project is complete.
- SUB-PROJECT
LP1.1 - Thomas N. Lay Park - Resurface Paved Surfaces: This sub-project
consists of providing new asphalt surfaces to the service drives, and
basketball play areas for this park. This project will be accomplished
utilizing the asphalt crews of the Public works department. Status:
Project is complete.
- SUB-PROJECT
LP4.1 & 5.1 - Thomas N. Lay Park - Interior and Exterior Lighting:
This sub-project consists of providing new interior and exterior lighting
to the community center at this park. Materials are to be purchased
and installed utilizing Leisure Services department staff. Status:
Project is complete.
- SUB-PROJECT
LP6.1 & 7.1 - Thomas N. Lay Park - Picnic Shelter and General Site
Equipment: This project will consist of the purchase of a Premanufactured
20 foot by 30 foot Picnic Shelter and related tables and chairs. This
project will be quoted utilizing approved A-CC Purchasing requirements.
Status:
Project is complete.
- SUB-PROJECT
EACP2.1 & 3.1 - East Athens Community Park - Interior and Exterior
Lighting: This sub-project consists of providing new interior and
exterior lighting to the community center at this park. Materials are
to be purchased and installed utilizing Leisure Services department
staff. Status:
Project
is complete.
- SUB-PROJECT
EACP4.1 & 6.1 - East Athens Community Park - Renovate Softball Field:
This sub-project consists of regrading the existing Softball Field at
this park. It will also include re-working of the storm drainage system,
sprigging of grass for the field, field irrigation, and a new backstop.
This project will be bid concurrently with the East Athens Tech. Park
project being sponsored by the Human and Economic Development department.
Each project will receive independent pricing as part of this bid package
and has the right to either utilize one contractor for both projects,
separate contractors for each project, or each projects has the right
to not accept a bid. Status:
Project is complete.
- SUB-PROJECT
EACP5.1 & 7.1 - East Athens Community - Park Picnic Shelter and
General Site Equipment: This project will consist of the purchase
of a Premanufactured 20 foot by 30 foot Picnic Shelter and related tables
and chairs. This project will be quoted utilizing approved A-CC Purchasing
requirements Status:
Project is complete.
- SUB-PROJECT
ROSP3.1 & 4.1 - Rocksprings Community Center - Roof Repair &
Interior Renovations: This project includes re-working the existing
roof over the front entrance, construction of two new ADA accessible
restrooms, new exterior doors and hardware, new HVAC equipment, painting
of interior, re-working of interior ceiling and replacement of certain
windows. This project will be quoted utilizing approved A-CC Purchasing
requirements. Status:
Project is complete.
GROUP
C - SUB-PROJECTS DESCRIPTIONS:
- SUB-PROJECT
SCP6.1 - Sandy Creek Park - General Site Equipment: The existing
Park will receive new Site Equipment such as picnic tables, trash receptacles,
surface mounted benches, and fire rings and mounts. These items will
be purchased and installed under one contract and receive quotes utilizing
normal A-CC Purchasing requirements. Status: Project
is complete.
- SUB-PROJECT
BP4.1 - Bishop Park - Resurface Asphalt Walkways: This sub-project
consists of resurfacing or replacing the existing walkways located within
this park. The amount of walkways that will be completed will depend
upon allocated funds. This construction will be accomplished under one
contract and quotes will be received utilizing normal A-CC Purchasing
requirements. Status:
Project is complete.
- SUB-PROJECT
BP6.1 - Bishop Park - Replace Chain Link Fencing: This sub-project
consists of replacing portions of the existing Chain Link Fencing around
the perimeter of the Ballfield. This construction will be accomplished
under one contract and quotes will be received utilizing normal A-CC
Purchasing requirements. Status:
Project is complete.
- SUB-PROJECT
BP9.1 - Bishop Park - Six sets of Bleachers: This sub-project consists
of purchasing Six sets of Bleachers to be utilized at various locations
throughout the Park. Leisure Services Department Staff, utilizing normal
A-CC Purchasing requirements, is accomplishing the purchase and installation
of this project. Status:
Project is complete.
- SUB-PROJECT
BP10.1 - Bishop Park - Two Roof Top HVAC Units: This sub-project
consists of the purchase and installation of Two new Roof Top HVAC Units
to replace existing ones on the Gymnasium. Leisure Services department
staff, utilizing normal A-CC Purchasing requirements, is accomplishing
the purchase and installation of this project. Status:
Project is complete.
- SUB-PROJECT
BP11.1 - Bishop Park - General Site Equipment: This sub-project
consists of purchasing new Site Equipment such as Picnic Tables, Grills,
and Trash Receptors to replace existing ones at this park. Leisure Services
department staff, utilizing normal A-CC Purchasing requirements, is
accomplishing the purchase and installation of this project. Status:
Project is complete.
- SUB-PROJECT
MP7.1 - Memorial Park - General Site Equipment: This sub-project
consists of purchasing new Site Equipment such as Picnic Tables, Grills,
and Trash Receptors to replace existing ones at this park. Leisure Services
department staff, utilizing normal A-CC Purchasing requirements, is
accomplishing the purchase and installation of this project. Status:
Project is complete.
- SUB-PROJECT
SAP2.1 - Satterfield Park - Replace Bleachers: This sub-project
consists of purchasing Eight sets of Bleachers to be utilized at various
locations throughout the Park. Leisure Services department staff, utilizing
normal A-CC Purchasing requirements, is accomplishing the purchase and
installation of this project. Status:
Project is complete.
- SUB-PROJECT
SAP3.1 - Satterfield Park - Playscape: This sub-project consists
of providing new Playground Equipment at this park. Materials are to
be purchased and installed utilizing Leisure Services department staff.
Status:
Project is complete.
- SUB-PROJECT
BURP1.1 - Burton Park - Emergency Vehicle Access: This sub-project
consists of replacing an existing security gate into the park with a
new modern electric Emergency Vehicle Access / Security Gate. Furthermore,
it will be the intent of this sub-project to also provide necessary
security restraints for other potential entry points into this park.
Quotes will be received for the purchase of materials and installation
utilizing normal A-CC Purchasing Department requirements. Status:
Project is complete.
- SUB-PROJECT
BURP4.1 - Burton Park - General Site Equipment: This sub-project
consists of purchasing new Site Equipment such as Picnic Tables, Grills,
and Trash Receptors to replace existing ones at this park. Leisure Services
department staff, utilizing normal A-CC Purchasing requirements, is
accomplishing the purchase and installation of this project. Status:
Project is complete.
- SUB-PROJECT
ROSP5.1 - Rocksprings Community Park - General Site Equipment: This
sub-project consists of purchasing new Site Equipment such as Picnic
Tables, Grills, and Trash Receptors to replace existing ones at this
park. Leisure Services department staff, utilizing normal A-CC Purchasing
requirements, is accomplishing the purchase and installation of this
project. Status:
Project is complete.
- SUB-PROJECT
NORP1.1 - North Oconee River Park - Increased Parking: This sub-project
consists of the design and construction of parking for this park. Currently
there s no parking for this park. It is proposed to include the construction
of 10 to 15 parking spaces. At a minimum, one ADA accessible parking
space will be constructed. The construction will be accomplished by
an outside contractor utilizing normal A-CC Purchasing Department requirements.
Status:
Project is complete.
- SUB-PROJECT
YSCPX1.1 - Youth Sports Complex - General Site Equipment: This sub-project
consists of purchasing new Site Equipment such as Picnic Tables, Grills,
and Trash Receptors to replace existing ones at this park. Leisure Services
department staff, utilizing normal A-CC Purchasing requirements, is
accomplishing the purchase and installation of this project. (The
Leisure Services Department has decided that, in lieu of above identified
scope of work, HVAC should be provided for the existing concession buildings.)
Status:
Project is complete.
Project
Design Consultant: Benchmark Design Intern’l
Sponsoring
Department: Leisure Services Dept.
Department
Director: Deborah Mockus
Associated
Organizations: None
Other
Interested Organizations: None
Verifications/Approvals:
- Mayor
& Chair & Commission: 05/06/97 - SPLOST Project Request
- SPLOST
IV Advisory Comm: 04/24/97 - Leisure Services Master Plan
- Manager’s
Office: 02/24/97
- Responsible
Department: 02/24/97
Current
Status:
Action
Since Last Report:
Project is complete.
|