PROJECT
17 - NORTH
OCONEE RIVER GREENWAY - PHASE I
PHASE 1 - DIVISION A & B
See
how Phase I fits into the full proposed Greenway with this full map.
Campaign
Statement: Acquire and begin appropriate development of the wetlands
and bottom land tracts along the North Oconee River which will provide
a variety of outdoor recreational and educational opportunities, and safe
alternative transportation including pedestrian and bicycle paths.
Project
Location: Riverfront properties along the North Oconee River Corridor
within the boundaries of Athens-Clarke County Urban Section.
Original
Project Budget: $ 1,977,000
Additional
Funding:
Additional
Outside Funding: $ 693,600 (TEA Funds)
Revised
Project Budget: $2,670,600
Operating
Budget Impact: $30,000.00/Year
PROJECT
CONCEPT: The scope of this Phase I Construction package consist of
the following:
- A poured
concrete multi-use bicycle/pedestrian pathway, which will provide
a natural experience that will be enjoyed by many along the North
Oconee River.
- Project
is to be divided into a Division 1A and a Division 1B where Division
1A's termini is from the intersection of East Broad Street and Willow
Street to Privately Owned Property adjacent to the perimeter (property
and/or right-of-way along this Division is currently owned by ACC)
and Division 1B's termini being from the end of Division 1A to Sandy
Creek Drive (property and/or necessary easements currently are owned
by private individuals and will require acquisition by ACC). Both
Divisions will be bid as one Bid Package and Division 1A will begin
construction immediately after award of contract and Divsion 1B will
begin after land acquisition is completed.
Project
Design Consultant: Robinson Fisher Assoc.
Sponsoring
Department: Leisure Services Dept.
Department
Director: Deborah Mockus
Associated
Organizations: Oconee Rivers Greenway Commission, Chairman: Dick
Fields
Other
Interested Organizations: RiverCare
2000 Land Trust
Verifications/Approvals:
- Mayor
& Chair & Commission: September 7, 1999 - SPLOST Project
Request
- SPLOST
IV Advisory Comm: August 4, 1999 - Heritage Trail Charette dated
2/26/94
- Manager’s
Office: July 22, 1999
- Responsible
Department: July 13, 1999
Current
Status: Project is complete.
Action
Since Last Report:
| Divisions |
Description |
Construction
Period |
| Division
1A |
Willow
Street Trail |
Complete |
| Division
1B |
Sandy
Creek Connector |
Complete |
| Division
1C |
Sandy
Creek Bridge
|
Complete |
|