What's New in ACC All About Athens-Clarke County Judicial Branch and Courts Other Links of Note in ACC A Virtual Tour of ACC Landmarks ACCent Newsletter Online ACC Departments Pay Your Bills Online Where/How To... SPLOST Program Info Directory and Contact Information Mayor and Commission Info Return to Home Page
SPLOST IV Progress Reports
What's New in ACC All About Athens-Clarke County Other Links of Note in ACC A Visual Tour of ACC Landmarks ACCent Newsletter Online Where / How Do I . . . ? SPLOST Program Info Directory and Contact Information Mayor and Commission Info Return to Home Page

PROJECT 22 - BARNETT SHOALS ROAD WIDENING AND DRAINAGE

NOTE:  See Also SPLOST 2000 Project #23:

Local Road Improvements Projects

Campaign Statement: Widening of Barnett Shoals from Greencrest Drive to College Station Road from a four-lane to a five-lane, installing an extensive storm drainage system, and adding sidewalks on both sides.

Project Location: Barnett Shoals Road from Greencrest Drive to College Station Road.

Original Project Budget: $ 1,200,000

Additional SPLOST Revenues & Earned Interest Allocated: $1,716,533

Additional Outside Funding: $0

Additional Funding: $10,000

Revised Project Budget: $2,926,533

Operating Budget Impact: None

REVISED GENERAL PROJECT CONCEPT: The scope of this project is to improve drainage, improve traffic operations and capacity, and increase vehicular, bus, bike and pedestrian safety through geometrical improvements and implementation of traffic management techniques. The roadway portion of this project shall be on Gaines School Road from Hilsman Middle School to the future ACC Fire Station No. 7 (near the intersection of Clarke Drive and Barnett Shoals Road), a distance of approximately 1.2 miles. This project will also evaluate the possible implementation of parallel access roads and inter-parcel connectivity. This project also includes a drainage system to manage the stormwater runoff in this area. SPLOST funding will be expended in the following priorities: 1.) Detail evaluation of improvement alternatives; 2) Design of roadway and drainage improvements; 3.) Acquisition of required right of way; 3) Construction of these improvements.

Project Design Consultant: Arcadis Geraghty & Miller

Sponsoring Department: Transportation & Public Works

Department Director: David Clark

Associated Organizations: None

Other Interested Organization: None

Verifications/Approvals:

  • Mayor & Chair & Commission: 05/02/00 - SPLOST Project Request
  • SPLOST IV Advisory Comm: 11/18/98
  • Manager’s Office: 11/18/98
  • Responsible Department: 11/18/98

Current Status: Phase IV - Construction

Action Since Last Report:

Documents:

Comments: SPLOST IV Project #6 – General Intersection Improvements – sub-project – Cedar Shoals Drive @ Gaines School Road has been combined with this project for design / construction purposes and will be partially funded by GDOT and FHWA.