PROJECT 06
- GENERAL INTERSECTION IMPROVEMENTS
GROUP A
Campaign Statement: Improve
intersections throughout Athens where increased traffic flow has caused
congestion during peak periods.
Project Location: Selective
intersection locations where increased traffic flow has caused congestion
during peak periods.
Original Project Budget:
$ 1,200,000
Additional SPLOST Revenues Allocated:
$ 1,272,000 (Amendment
1 - June 15, 1999)
Additional
Outside Funding: $ 2,770,776
(eligible for Federal-Aid), $ 6,024 (reimbursement for PM Fees) = $ 2,776,800
total
Revised
Project Budget: $ 5,248,800
Operating Budget Impact: None
PROJECT DESCRIPTION: The
Project Description consists of three intersection improvement projects.
They are as follows:
- 1. Indian Hills Drive and
Winterville Road at Spring Valley Road: Winterville road is to be
relocated to line up with Indian Hills road at Spring Valley road. Right
and left-turn lanes are to be designed in each quadrant of the proposed
intersection. Spring Valley road is to be realigned both horizontally
and vertically at the existing curve immediately northeast of the intersection.
The CSX railroad has been abandoned and the tracks have been removed.
- 2.Moss Road and Athena Drive
at Spring Valley Road: Moss road is to be relocated to line up with
Athena Drive at the Spring Valley road intersection. Moss road is to
be designed with a right-turn and a left-turn lane. Athena Drive and
Spring Valley road will be widened to provide for left-turn lanes. Anderson
Lane is to be realigned at Spring Valley road to provide better angle
of intersection.
- 3.Winterville Road at Nellie
B. Avenue: Nellie B. Avenue is to be realigned at Winterville road
to provide a 90-degree intersection. Winterville road and Nellie B.
Avenue will be widened to provide left-turn lanes. A sidewalk is to
be designed on the north side of Nellie B. Avenue from Winterville road
to Andrea Drive.
Project Design Consultant:
Kimley-Horn and Associates, Arcadis Geraghty & Miller
Sponsoring Department:
Transportation & Public Works
Department Director: David
Clark
Associated Organizations: None
Other Interested Organizations:
None
Verifications/Approvals:
- Mayor & Chair & Commission:
11/02/99- SPLOST Project Request
- SPLOST IV Advisory Comm:06/02/99
- Manager’s Office:05/24/99
- Responsible Department:05/20/99
Current
Status: Phase IV - Construction
Action Since Last Report:
- Nellie
B. at Winterville Road Project:
Project is complete.
- Indian
Hills at Spring Valley Road:
- Construction
was awarded to E. R. Snell and has been turned over to GDOT for
completion.
- Construction
is underway. Clearing and Grubbing is complete and rough grading
is on hold pending utility relocation.
- Construction
is expected to be complete in June 2006
- Moss
Road /Athena Drive at Spring Valley Road: Project
is complete.
|