Project 10: Whitehall Road at S. Milledge Avenue Project

Project Details

Whitehall Road at S. Milledge Avenue Project, includes construction of intersection improvements to the traffic operations and safety at the intersection of Whitehall Road / S. Milledge Avenue. Design of the project is being included in SPLOST 2011.

Project Updates

All scheduled utility relocation has been complete, with the exception of AT&T which is scheduled to be complete by the end of May. The contractor has developed a staging plan that will not require the intersection to be closed completely; the remainder of the project will be constructed with minor traffic delays.

*as of 5/15/2019

Estimated Costs:  
TSPLOST 2018 Budget
$2,500,000