Sub Project 1: MLK, Jr Parkway Culvert Replacement
This project is complete.
Sub-Project 2: FY18 Bridge Improvements
Project Details: Phase I includes the structural repair & maintenance of 6 bridges as recommended by a biannual inspection conducted by GDOT. On May 1st, 2018, M&C voted to award the contract to Sun Coast Restoration & Waterproofing, LLC. Construction is in progress.
Update: A notice to proceed was issued to Sun Coast Restoration & Waterproofing, LLC on June 1, 2018. The contractor has completed repair work on Fowler Road Bridge, Cleveland Road Bridge, E. Broad over the N. Oconee River, North Avenue Bridge over the N. Oconee River and Macon Highway over the Middle Oconee River. Consultants are identifying additional repairs needed on 15 other bridges. Phase 2 of this project includes additional bridges to be assessed and repaired with remaining budget and available resources. Staff identified maintenance and repair needs on 4 additional bridges that will be addressed with lane restrictions and lane closures only: