Sub-Project 1: Cherokee Road

Project Details

Connect a sidewalk gap on Cherokee Road between Lexington Road to Beaverdam Road on the southeast side of the road to avoid an existing cemetery. Pedestrian access to Satterfield Park will also be considered. Connection points to the existing sidewalk are at Morning View Drive and 360 feet down Beaverdam Road Project length is approximately 3,700 feet. 

Project Updates

Purchase Order has been issued and conceptual designs are underway. Concept design was presented to the public for comment on October 14, 2019 and will be presented to M&C at work session on November 12, 2019. M&C action on the proposed concept is expected at the December cote meeting.

*as of 10/15/2019